This websites use cookies. By continuing to browse the site you are agreeing to our use of cookies. For more details about cookies and how to manage them, see our cookie policy.

Sector: Education
Service: Cost Consultancy | Project Management | Principal Designers

Fulfilling a vision to rebuild St Bonaventures Primary School 

The Governors of St Bonaventure’s school had a vision to rebuild the whole of the existing 1960’s school which was no longer fit for purpose both in design and condition. The school had been designed for 210 pupils when first constructed and had since been extended, largely by the introduction of prefabricated classrooms, to accommodate 420 pupils. A scheme was developed in the early part of the new century which would see the school rebuilt in phases as the school continued to operate on a very restricted site and funding was achieved to begin. A planning application was approved for the whole scheme, and two initial phases constructed.

The challenge

The financial landscape changed and the level of funding available was significantly reduced. The Board of Governors secured funding in 2012 to complete the replacement of the existing school buildings however they obtained significantly less than was required to complete the original design. It was therefore necessary to undertake a complete re-evaluation of the design to allow completion of the works within the available budget which required the overall anticipated cost be reduced by over 20%.

The solution 

As Project Managers and Cost Consultants Hookway led the re-evaluation and value engineering of the proposals and helped produce an affordable design. To achieve this the practice liaised with the Governors and the design team to re-evaluate the brief to focus the budget on the essential requirements. One particular element was the removal of the steel frame and the construction with load bearing blockwork. We evaluated and recommended that a Design and Build contract was the most effective contract solution. We then prepared and issued contracts under the JCT Design & Build Contract for this work. We provided detailed reports on the Contractor’s Proposals and assessed alternative contractor’s proposals provided at tender stage. We then helped develop a strategy for procurement which saw an enabling works contract for demolition being implemented whilst Phase 1 of the rebuild was tendered. Thus keeping the overall scheme on programme.

The second phase was developed whilst Phase 1 was under construction, this required carefully monitoring of both the Phase 1 contract costs and the proposals for Phase 2 to ensure that the works remained on budget.

Rigorous cost evaluation of the design proposals led to Phase 2 being constructed with a timber frame, as the cost profiles no longer favored blockwork. Procurement of Phase 2 was developed with a twin strategy, the first to negotiate the second phase with the on-site contractor whilst at the same time developing a traditional tender package. In the event the contract was awarded to the Phase 1 contractor as an extension to the original contract.

The result 

The works were completed on time and on budget thanks in no small part to the flexibility and rigor of the cost management. 

Related case studies

St Peter's School

Hookway was appointed to prepare a bid for government Condition Improvement Funding (CIF) to refurbish the 12 classroom English Block for St. Peter's School.

Read full case study

Christ Church Primary school

Hookway helped Christ Church CofE Primary School secure Healthy Pupils Condition Improvement Funding, and install a fabulous new Multi-Purpose Games Area.

Read full case study

CIF 2019 - project round up

Hookway's surveyors worked on numerous CIF projects for schools and academies in 2019, ensuring that all work was completed in time for the start of a new academic year.

Read full case study

Testimonial

“Hookway have been excellent and our English block looks and feels like a new building. ”

“The needs of the school were always at heart and I felt that I had a voice in the process. The two new classrooms are fantastic. They are light, airy and spacious, and the children love them. The children refer to them as the ‘Posh Wing’.”

“Hookway have worked in collaboration with us to deliver this transformation project and have provided regular clear communication throughout which has helped with the smooth running of the project. The project team have all played a vital role in this year-long programme and we’re delighted the project has finished on time and on budget.”